Environment Effects Statement
Why were the Sydenham Terminal Station works removed from the project scope?
The Sydenham Terminal Station Rebuild was planned to be undertaken at the same time as the Western Renewables Link works. As a result of delays to the Western Renewables Link project, the urgent asset replacement works at Sydenham Terminal Station must be delivered prior to the Western Renewables Link works to maintain reliable transmission services in Victoria.
Construction of a new terminal station north of the existing Sydenham Terminal Station no longer forms part of the project, though the Western Renewables Link will still need to connect into a terminal station at that location. These connection works will be included in the Western Renewables Link Environment Effects Statement assessment.